ERG was commissioned by Trustmark National Bank to improve their chilled water system reliability and energy efficiency. ERG designed a complete Central Utility Plant Building Automation System (BAS) retrofit which included optimization of the all variable speed chiller plant. The chiller plant BAS includes state of the art control sequences designed to optimize energy and plant reliability.

ERG is performing ongoing research and commissioning of the plant to ensure sustainable system performance. Additionally, ERG has performed a chilled water and heating water system master plan studying short-term and long-term system improvements and retrofits.

Project Type

Central Plant

Size

1,000 ton cooling

Services Provided

Mechanical design, control system design, commissioning and energy management. 3-D modeling of building and mechanical systems.

Completion Date

2017

Owner

Trustmark National Bank

Location

Jackson, MS